From the outset, our thesis was that Green Building isn't expensive.
Many people before us have done life cycle analysis and found that over the
lifetime of the building, Green Building often saves money. We went one step further, and claimed that we could build a house that is very
green for less than ten percent additional cost up front. While we still
may be able to reach that goal, we discovered that there are many complicating
factors so some context is needed.
Although we thought that stating the cost of green building as a percentage
of construction cost would make it a more generally applicable metric, we
realized that this is totally false. The problem is that the cost of
construction varies greatly throughout the country, while the cost of many green
products is very similar throughout the country. In Seattle, the cost of
houses and construction is one of the highest in the country, so the relative
cost of green products is less. Of course, any aspect of green building
that involves mostly labor will scale in price with the cost of
construction. Rather than trying to draw generic conclusions, we present
an analysis of our costs an let you draw your own conclusions.
For those not familiar with the local housing market, the entry price for a
house is just over $300K, and a typical medium size home goes for $450K or
more. Typical construction prices range from $125/SF to $200/SF of
finished space, depending on the complexity of the house and the cost of finish
materials. Our initial thought had been to do an extensive remodel
and second story addition with a target price of around $250K, but as the scope
changed to be a complete re-build, the price shot up about $425K, which is in
the range of construction costs, but when added to land cost, higher than what
could get back if we sold the house on the open market (and if you add the cost
of the existing house, which we have to pay to have removed, the situation is
worse, but we knew that up front).
The majority of this budget is independent of Green Building, and can be
mostly attributed to three factors:
-
The size of the project (about 2500SF finished space, 300SF attic space,
1000SF basement and garage.)
-
The high cost of construction (see note below)
-
The fact that we also building an ADU.
While this accounts for most of the budget, there are a few other significant
issue affecting cost:
- Green building typically involves higher quality, longer lasting products
and by nature requires greater attention to detail, and hence more experienced,
higher priced labor. This affects such things as energy performance and
longevity of the building.
- Although not strictly necessary, Green Building often involves a higher
level of finish detail because aesthetics are also important to many people.
- When building a smaller home, the cost per square
foot tends to go up, because there are many fixed costs in a house, no matter
what size it is.
There are two economic twists that compound the cost issue: first, although
the economy has a whole is in the middle of a big downturn, construction has not
been affected by this because it has been buoyed up by very low interest rates,
making it seem relatively expensive. The other interesting issue is that
the state of Washington charges sales tax on construction, at 8.8%, or about
$34K out of the $425 total budget. While we have no particular political
opinion as to whether this is a reasonable method of taxation, it did occur to
us that this amount was approximately how much we thought the additional up
front cost of the green features of the house would be.
Ignoring all these issues, we believe that our construction costs are very
comparable to other custom construction projects. If we guess at $50K for
the cost of the unfinished space, that leaves $375K or about $150/SF.
Rather than look at overall costs, it is useful to attempt to break out the
additional costs of green building as line items. For a discussion on the benefits of the various materials, see the next
section.
|