|
Anyone who is familiar with green construction has a love-hate relationship with
concrete. Like wood, it is a universal building material that ends up in
building off all types in some way or another (even most straw bale
houses). The most significant problem with it is the amount of energy used
to make it, and then cart it around. We are using a flyash mix (for more
on concrete, see materials section ), which reduces the energy use significantly, but certainly doesn't
make it a low energy product.
Although flyash mixes are often stated as to the percent of flyash of the
total of flyash plus cement, this is misleading unless it is specifically stated
that the flyash was used to replace cement (see flyash discussion in materials
section)
Our usage is as follows:
| Location |
Amount Used |
Mix Used |
Normal Mix |
| Footings |
7 yards |
43% flyash: 350lbs cement, 150lbs flyash |
500 lbs cement |
| Walls |
24 yards |
43% flyash: 350lbs cement, 150lbs flyash |
500 lbs cement |
| Slab |
22 yards |
20% flyash: 400lbs cement, 100lbs flyash |
500 lbs cement |
| Rainwater tank |
14 yds? |
|
|
| Retaining walls |
TBD |
|
|
| Footing pads |
TBD |
|
|
According to statistics from the National Association of Homebuilders (1998
data), the average house built that year is 2085 sq ft and uses 14 tons of
concrete (or about 7.5 yards), which is dramatically lower than what we used
(reference: EBN V8#1, Jan 1999). However, when we compute how much
concrete we expect a house to use, we get a much different number.
Although we didn't find the concrete use statistic on the NAHB website, we did
find characteristics of homes from that year: average home size was 2190
sq ft (median was 2000), 48% of which were one story homes. As for
foundations, 37% had a full or partial basement, 43% were on a slab and 78% had
at least a two car garage.
Although there are a variety of configurations, the fact that 80% had a
basement or were on a slab, and 78% had a two car garage, it would seem
reasonable to assume that the average home had at least a 1000 sq ft of concrete
floor. Since a typical slab floor is at least 4" thick, we can
calculate the concrete use as 1000/3=333 cu ft, or 12.3 yards. Then, all
the load bearing sections have to be thickened to have footings, which at about
120 linear feet footing that uses at least .75 cu ft of concrete/linear foot (ie
the footing is 8" deep and 12" wide), that adds another 3.3 yards,
bring us to a total of 15.6 yards, all using what would seem like very
conservative guesses, and still resulting in double the use reported.
If anyone has better numbers, please contact us.
Analyzing our Usage
Even ignoring the concrete in the rainwater tank, we used a lot of
concrete. There are two classes of reasons of why we used so much
concrete: choices we could have made, and issues with structural engineering and
building codes.
We could have chosen not to build a basement at all (see design
for why we did), and we also could have used ICFs for the foundation (we didn't
because they cost a lot more). But that leads to the question of why an
ICF walls with much less concrete is deemed sufficient, but a six inch thick
foundation, which still uses more concrete than an ICF wall, isn't (we had to
use 8" thick walls).
Structurally, both the footings and the slab consumed what seemed like
excessive amounts of concrete. The footings are 18" wide and 9"
deep and filled with re-bar, although their only task is to spread the load of
the foundation over a bigger area to prevent it from sinking into the
ground. It seems like there ought to be a way to use little to no concrete
by substituting rock, broken concrete, crushed stone etc. A significant
amount of the concrete use in the slab is for areas where it is thickened to
provide an integral footing. Without these footings, the slab would have
used only about 13 yards of concrete. Again, the thickened slab footings
seem like huge overkill, and that there ought to be a better way.
In general, it would appear that the world really is in need of a green
structural engineer to come up with creative solutions to using less concrete.
The amount of flyash that can be used depends both on the kind of flyash
that's available and the ability of the concrete finisher to deal with its
unique finishing properties. Walls cure in the forms, so don't present
much problem, but slabs require a different technique for any significant amount
of flyash. The concrete finishers didn't like working with our 20% flyash mixture
because of this, but in spite of
their complaining, our untrained eye thought the finished slab came out as
smooth as anyone would want.
Embodied Energy Usage
The energy to produce 5 sack concrete is usually given as around
1.5mBTU/yd. In EBN
V2#2 (mar/apr 1993), the energy use is given as 1.7mBTU/yd, but the
assumptions behind this number includes transportation the materials to the
plant, and transportation of the cement to the job. Since 94% of this
embodied energy is in the Portland cement, reducing the amount should save
energy, but the flyash also must be transported so the cost isn't zero.
Using numbers from EBN V8#6, train transport is about 310kBTU/ton or
15.5kBTU/100 lbs. Compared to the total energy use this is so
insignificant that it can be ignored (these numbers have so many assumptions
built into them, they aren't that accurate anyhow). So if five sacks of
Portland cement uses 1574kBTU then 1 sack uses 315kBTU.
(final embodied energy calc goes here)
Foundation Drainage
The biggest issue with building below ground is keeping ground water out of
the building, and this is complicated by the fact that concrete absorbs water
and will wick it upward for a long way. We use two main strategies to keep
water out:
- Surround the concrete with rapidly draining material, such as gravel.
- Put a water barrier on the concrete itself.
|
|
Polyethylene capillary break under the footing.
|
While some aspects of these strategies are normally used, standard practice does not create
a complete barrier to ground water entry into the foundation, and we wanted to
do that: mostly because we think its a good idea, but also because the
forthcoming IEQ standard being created by the EPA requires that these extra
precautions be taken. Given the frequency of mold problems in house, and
the ubiquitous nature of water in basements, it seems likely that standard
practice is going to include additional strategies for preventing groundwater
infiltration, although they may not be the ones we've used.
Our first new technique is to install a capillary break so that water doesn't
wick up the footing and into the foundation. Since our footings are
sitting on nearly pure clay which holds water but doesn't drain it well, that
this was a reasonable precaution and after some consultation, it was decided
that a polyethylene sheet under the footing would do the trick.
Traditional construction relies on using gravel both inside and outside the
footings to drain water away from the footing, but this does nothing to prevent
water from coming up through the footing via capillary action. We would
expect this technique, or something like it to become standard since it is low
cost and easy to do.
|
Delta-drain material attached to foundation and footing drain in
place (left). The footing drain will get covered in gravel and a filter
fabric before backfilling. Gravel under the slab (right). The dirt
area in the center is a footing under the central load bearing walls. This
is obviously a weak spot for water, since there is no gravel under it. Cross
sectional diagram of foundation wall (middle).
|

|
The only other significant difference is in using a drain fabric on the
outside of the foundation. We used Delta-drain, which is a heavy weight
(but still somewhat flexible) plastic material that is composed of a sheet of
plastic molded like hundreds of little egg cartons that faced the concrete and a
plastic filter fabric on the dirt side (see photo, above. The black
material came off a different spool, but has the same egg carton plastic under
it.) The idea is that the delta-drain creates air gaps that won't hold
water or promote capillary action (just like the gravel). This keeps
ground water away from the foundation. It is fine if water gets behind the
delta drain, since the wall is sealed with Thoroseal, and any water that gets
back there will quickly drain down in the footing drain.
The main issue is keeping dirt from keep between the concrete and the
delta-drain & in between the layers of the delta drain. Since the
layers are bonded together, dirt will stay out as long as the filter fabric
isn't punctured by either shovels or plant roots. The area between the
concrete and the drain material is more problematic, since the drain material is
attached by nails. While it is probably possible to get the drain material
tight to the wall, it isn't easy and dirt will likely fall down through any
small crack that is left. The instruction say to install is "at
grade", but our experience is that "grade" can easily change over
the lifetime of a house due to the addition/removal of topsoil and mulch.
It would seem like a better idea to embed a strip of some sort into the concrete
(ie before the pour), and then snap the drain material into the attachment
strip, thereby creating a continuous dirt barrier.
Our sales rep suggested we use the delta drain over the footing as well, but
this proved to be very frustrating because the delta drain does not bend all
that well, and wouldn't conform well. In addition to this, it was
difficult to install the material around corners. Overall it seems like a great
idea that could use a little work.
Although the basement is designed to be unheated, unfinished space, we
installed perimeter insulation under the slab in case someone wanted to use the
space in the future.
|
|
|
Vapor barrier & perimeter insulation on top of gravel
(left). Pouring the slab (right).
|
|