Seattle - Construction

Each phase is documented separately, in roughly the order they were done in.  Additional info about each section is available in the tutorial and in the design section.


Construction Phase Begin Date
Deconstruction June 9,2003
Excavation July 1,2003
Concrete July 7,2003
Framing July 28,2003
Rainwater Tank Aug 4,2003
Roofing Aug 31,,2003
Rough Plumbing Aug 25,2003
Siding/Windows Sep 5, 2003
HVAC Sept 5,2003
Rough Electrical Sept 9,2003
Insulation Sept 22,2003
Sheetrock Sept 26,2003
Appliances n/a
Finish Materials Oct 2003
Landscape July 2004
Solar Electric July 2005